October 18, 2013
Mount Pleasant Road bridge over Rosedale Valley Road re-opened
  
The Mount Pleasant Road bridge over Rosedale Valley Road is now fully re-opened to traffic. After 18 months of construction, the project is on budget and the work was completed on October 11.

"Mount Pleasant Avenue is a critical piece of our road system. We'd like to thank the public for their patience while we made this important investment in our transportation infrastructure," said Councillor Denzil Minnan-Wong (Ward 34 Don Valley East), Chair of the City's Public Works and Infrastructure.

There will be short-term closures during the next two weeks for some minor cleanup work. This work will be completed by October 31.

The contract price was $5.2 million (excluding HST), but the actual cost for the project came in at approximately $5.0 million.

Toronto is Canada's largest city and sixth largest government, and home to a diverse population of about 2.8 million people. Toronto's government is dedicated to delivering customer service excellence, creating a transparent and accountable government, reducing the size and cost of government and building a transportation city. For information on non-emergency City services and programs, Toronto residents, businesses and visitors can dial 311, 24 hours a day, 7 days a week.


Media Contact
Steve Johnston, Senior Communications Co-ordinator
Strategic Communications
416-392-4391
sjohnsto@toronto.ca

 

 

Toronto maps | Get involved | Toronto links
© City of Toronto 1998-2017