April 11, 2001
Construction work on Yonge Street resumes
  
Works and Emergency Services -- Work to replace sidewalks, curbs and gutters on
Yonge Street from St. Clair Avenue to Roxborough Street East and from Eglinton
Avenue to Roehampton Avenue (on the west side of Yonge Street) will take place
beginning April 16 and continue until mid-June, 2001.

The project also involves the resurfacing of Yonge Street from St. Clair Avenue
to Roxborough Street East.

The sidewalk, curb and gutter work will begin on April 16 and continue until
late May. The road resurfacing will take place starting in late May and is
expected to be completed by mid-June.

Throughout the duration of the project, at least one lane of traffic will be
open in each direction at all times. Access to bus and subway stops, as well as
to businesses, churches and residences, will also be maintained.

Work will be performed from 7 a.m. to 5 p.m. Monday through Friday. When
required, work will also be done Saturdays and evenings.


Media Contact
Access Toronto
416-338-0338

 

 